Shangdong Guangjun Paper – annual energy savings up to 32 %

Share this article

Energy saving 32% & water saving 63%

Client: Shandong Guanjun Paper mill

For Shangdong Guanjun Paper the project was delivered as turnkey ESCO (energy service company) project. The key technology provider was Runtech Systems. ABB‘s frequency converter was also used for the project. The delivery time of the energy efficiency project was only four months.

GreenStream organized financing, technical solution, and engineering for the project.

Annual savings:

  • Electricity saving: 1926.6 MWh
  • Water saving: 18495 m3
  • Steam saving: 2652 t
  • Standard coal: 1068 TCE
  • Emission reduction: 2766t CO2e

The main product of Shandong Guanjun is Cultural Paper with basis weight between 58 to 100g.

 

Photo by Faisal Al Fairs

Latest references

Opening China markets for Sarlin

GreenStream has opened China markets to many Finnish small and medium sized companies. One of the main technology partners at the moment is Sarlin.

Shangdong Guangjun Paper – annual energy savings up to 32 %

Annual savings:

Electricity saving: 1926.6 MWh
Water saving: 18495 m3
Steam saving: 2652 t
Standard coal: 1068 TCE
Emission reduction: 2766t CO2e

Energy Efficiency for Delong Steel

GreenStream’s project saved 15 % of the compressed air related electricity costs annually for Delong Steel’s Xingtai steel mill. The technology provider was Sarlin.